SK1 COMMERCIAL HUB

First Class Commercial Hub within Nusajaya's Silc

 

SK 1 Commercial Hub is a freehold commercial centre integrated within Nusajaya's highly coveted SiLC.
Featuring 68 exclusive units of 3 and 4 storey office suites as well as boutique hotel and office suites, SK 1 Commercial Hub is supported by world-class infrastructure within SiLC's dynamic business environment.

 

Nusajaya most Dynamic Commercial Hub

 

SKI Commercial Hub is set to be a hotspot for business within Nusajaya. Strategically positioned in a prime zone within the SiLC, SK 1 is only 15 minutes to Singapore via the Second Link while being highly accessible through a network of highways and main roads including Exit 309 from JB Parkway.

 

Here, your business space is only 10 to 15 minutes to Nusajaya's signature landmarks which includes Legoland, EduCity, Puteri Harbour and Medini. There's also a strong base of demand and fast-growing consumer flow of more than 60,000 residents from the matured surrounding residential developments that include Horizon Hills, Taman Nusantara, Ledang Heights, Setia Eco Garden and Taman Nusa Bayu.

 

Fronting the Nusa Perintis main road, SK 1 Commercial Hub enjoys superb connectivity via a major network of highways and main roads for fast and easy access to virtually everywhere. Increasingly, as Iskandar Malaysia continues to flourish, new and improved infrastructures will further enhance the support factors necessary for a sustainable commercial hub.

 

SK 1 Commercial Hub gives your business an attractive modern facade for a strong and instantly recognizable corporate identity. These innovative office suites is well-complemented by intelligently designed layouts that are both practical and functional.

 

As a dynamic and vibrant commercial hotspot, SK 1 Commercial Hub is ideal for various business concepts to meet the needs of a rapidly expanding community. The eclectic blend of business and leisure heralds a new style of life that is exciting and convenient.

Construction Progress Milestone

95%
Instalments Payable%Estimated Dates (Subject To Change)
1. Immediately upon the signing of the Sale and Purchase Agreement10DUE
2. Within fourteen (14) days after receipt by the Purchaser of the Vendor’s written notice of the completion of -
(a) earthworks of the said Building10JAN’14
(b) piling works of the said Building10MAY’14
(c) footing/pile cap works of the said Building5MAY’14
(d) reinforced concrete framework for the ground floor of the said Building – Ground Floor Beam & Slab5SEPT’14
(e) reinforced concrete framework for the 1st floor of the said Building – 1st Floor Beam & Slab5SEPT’14
(f) reinforced concrete framework for the 2nd floor of the said Building – 2nd Floor Beam & Slab5SEPT’14
(g) walls for the ground floor of the said Building with doors and window frames placed in position5NOV’14
(h) walls for the 1st floor of the said Building with doors and window frames placed in position5NOV’14
(i) walls for the 2nd floor of the said Building with doors and window frames placed in position5NOV’15
(j) roofing of the said Building5JAN’15
(k) electricity wiring and plumbing works (without fittings) of the said Building10MAR’15
(l) internal and external plastering of the said Building10APR’15
(m) drains and roads serving the said Building5MAY’15
3. Within fourteen (14) days of the date of the Vendor’s written notice that the construction of Building has been completed and that the Parcel is ready for delivery together with vacant possession to the Purchaser.5JUNE’15

2015-12

2015-10

2014-09

Structure: